The direction in this regard was issued by a division bench comprising Chief Justice Manjula Chellur and justice P R Ramachandra Menon on a PIL filed by one Suresh Babu seeking a direction to maintain 45 meters width of the national highway.
The bench said though land was acquired long back, widening work had not been completed so far.
The government informed the Court that there were some disputes on the matter of land acquisition.
Due to the delay, the loss is caused to the public exchequer, the court said and granted two weeks time to file affidavits.