The court had on June 19, 2014 directed that compensation be given for the land purchased from a private firm, as per the orders of the Collector on July 29, 2006.
Justice R Mahadevan today directed the officials to be present in the court within four weeks and submit an explanation for not following the court's direction.
Meanwhile, the Railways constructed a building and installed equipment in the acquired site.
The petitioner submitted that if the administration did not require the land, they should have removed the super structure and other equipment and handed the land over in the same condition as when purchased. But they did not do so.
Also Read
On July 29, 2006, the Collector directed Railways to give Rs 11.89 crore as compensation but no action was taken by the latter to give it, the petitioner said.
He then petitioned the Railways on January 1, 2014 to pay him compensation of Rs 20 crore and when nothing came of it, moved the court.
The court directed the GM to take into account the Collector's order to pay the compensation (Rs 11.89 crore) within six weeks.
Both the GM and the Deputy Chief Engineer sought time to implement the order and the court gave them eight weeks till August 13, 2014.
The petitioner said the officials had not issued any fresh notification on the land acquisition nor paid the compensation decided. It was illegal on their part to demand the land back and unfair on the part of the Chief Engineer to to ask him to again approach the Collector.
Hence, he sought a direction from the court to punish the two Railway officials for wilfully disobeying the court order.