A bench of Chief Justice G Rohini and Justice Rajiv Sahai Endlaw while issuing notice to the government and seeking its response by March 23, also said that auction of Gare Palma IV/2, IV/3 and IV/4 blocks in Chhattisgarh would be subject to the final outcome of the Jindal group companies' pleas.
The three coal blocks were earlier allotted to Jindal but the allocation was cancelled by the Supreme Court in August last year.
Senior advocate Rajiv Nayar, appearing for Jindal, prayed for passage of an order similar to those passed in the matters of GVK Power Ltd and Jayaswal Neco Industries Ltd, which had challenged the Ordinance provisions regarding method of determining compensation of capital costs, including mining infrastructure.
The petitions of Jindal group companies were moved a day after the high court gave them relief in their first set of petitions in which they had challenged change of end-use of two Coal blocks in Chhattisgarh and Odisha which had been earlier allocated to them.