"Its overall goal is to have 14.5 GWe (Gigawatt or one billion watts of electricity power) of nuclear generating capacity online by 2024, compared to 6,219 MWe now," said the World Nuclear Performance Report 2016 released at the Singapore International Energy Week being held this week.
The government gave in principle approval for new nuclear plants at 10 sites in nine states, according to the report by the World Nuclear Association.
Those for plants with foreign cooperation are Kudankulam in Tamil Nadu; in Jaitapur in Maharashtra; Chhaya Mithi Virdhi in Gujarat; Kovvada in Andhra Pradesh and Haripur in West Bengal, though this location has been in doubt.
In addition, two 600 MWe fast breeder reactors are proposed at Kalpakkam.
More From This Section
Unit 2 of the Russian-built Kudankulam nuclear power plant in Tamil Nadu was completed in 2015, with the unit continuing in mid-2016.
A prototype fast breeder reactor is nearing completion at Kalpakkam, according to the report.
The second unit of nuclear power plant in Rajasthan, which came into operation in 1981, performed more reliably, despite long outages between 1994 and 1998, and from 2007 to 2009. It achieved a lifetime capacity factor of 56 per cent. Rajasthan 3, starting in 2003, has managed a cumulative capacity factor of 76.5 per cent.
Altogether, the country has commissioned 18 Pressurised Heavy Water Reactors, two small BMRs - boiling water reactors - (in 1969) and two PWRs - pressurised water reactors - (at Kudankulam in 2014 and 2016, respectively), according to the report.
The association noted challenges of providing electricity across the world's rural regions where people lack electricity. It has set a higher target for nuclear power - 25 per cent of electricity in 2050, which would require an estimated 1,000 GWe capacity.
It said one possible pathway to this target would be to build 10 GWe a year between 2015 and 2020, step this up to 25 GWe per year to 2025, and then 33 GWe per year to 2050.