KG Tollway Pvt Ltd, a Special Purpose Vehicle (SPV) of IRB Infrastructure Developers Ltd, has successfully achieved financial closure for its Rs 1,526 crore BOT (build, operate, transfer) project of 6 laning of Kishangarh-Gulabpura stretch on NH-79," IRB Infrastructure said in a statement.
"Rs 1,020 crore has been tied up at a cost of 10.20 per cent per annum, with consortium of lenders led by State Bank of India, along with Yes Bank Limited, Bank of Maharashtra and IFCI Limited. IRB Infra will support the balance funding of Rs 506 crore through equity in the project," the statement said.
The project involves 6 laning of 90 km stretch on NH-79 between Kishangarh and Gulabpura in Rajasthan.
NH 79 connects Ajmer to Ghat Bilod, traversing through major settlement stretches such as Nasirabad, Gulabpura, Bhilwara, Chittorgarh, Mangalwara and finally Udaipur.
The company said the project entails annual premium payment of Rs 186.30 crore to NHAI, payment of which would commence after three years from the appointed date.