Four-laning works on Srinagar-Baramulla-Uri, which is scheduled for completion by July this year, has been delayed.
Handing over of road Sinathan Pass-Anantnag to NHAI will be postponed as the pending work on this road will now go beyond the planned September.
In addition, many vehicles/ equipment have been damaged, non-availability of which will directly affect the work efficiency.
The most affected locations where delay/loss of work has been seen are Tangdhar, Anantnag, Kupwara and Bandipur sectors, a statement by the defence ministry said.
More From This Section
"Movement and shifting of the material to forward areas have also hampered the work in Ladakh region which will severely impinge on the completion of strategic roads and spending of allotted funds," the statement said.
The ongoing unrest in Kashmir valley has adversely affected the road construction activities undertaken by Border Road Organisation, it said.
The Ministry stressed that BRO has suffered loss of working season, loss of more than three months of working season during summer is of serious concern, while endeavours are being made to execute work whenever and wherever possible.