"We will go for manufacturing of sponge iron from synthesis gas. This is first of its kind in the world. We expect to start the process by May 15," JSPL Chairman Naveen Jindal said after meeting Odisha Chief Secretary J K Mohapatra.
Stating that coal gasification has already started at the project site and the coal gasifiers are working very well, Jindal said that coal will be gasified and synthesis gas will be used for making sponge iron on the DRI (direct reduced iron) route.
JSPL has signed an agreement with Lurgi Technology Company of South Africa for providing technology for coal gasification. The DRI plant has a capacity of two million tonne per annum (mtpa).
JSPL's Angul steel plant, having capacity of 6 mtpa, has already commissioned its 2 mtpa plate mill.
Sources said the JSPL has been allotted Utkal-B coal block in the state with an estimated reserve of 228 million tonnes. It is awaiting permission from the state government to commence mining.