"JSW Group will invest Rs 3,400 crore in new projects besides the existing cement plant at Salboni (in West Medinipore)," Banerjee told reporters at the state secretariat after meeting JSW Group Chairman Sajjan Jindal.
The fresh investment would create 3,000 direct and indirect employment opportunities.
"In cement expansion, they will infuse Rs 700 crore, Rs 200 crore in captive power plant, decorative paints Rs 1,500 crore and Rs 1,000 crore in the downstream steel unit," she said.
The Jindals had agreed to return 294 acres purchased directly from farmers for the project but after they declined to accept the land, the group has decided to develop an agricultural project on the plot on cooperative basis with land owners being its members.
More From This Section
Jindal told reporters that the 2.4 million tonne cement plant will be completed by March.
"Project reports for other plans are underway and we expect in the next 2-3 years the new projects will get completed," Jindal said after the hour-long meeting with the chief minister.
The decorative paint plant will be of 2 lakh KL capacity and the downstream steel unit will be of 0.5 million tonne.
The steel would be sourced from either Maharashtra or Karnataka.
JSW Group will be able to strengthen its Karnataka steel plant after winning iron-ore blocks put on auction recently.