MADC could not develop any airport in Maha in 14 years: CAG

Image
Press Trust of India Mumbai
Last Updated : Apr 07 2017 | 7:22 PM IST
Despite 14 years of its existence, Maharashtra Airport Development Company (MADC) has not developed a single airport in the state due to absence of a long-term plan, the Comptroller and Auditor General has said.
The CAG report, tabled in the Maharashtra legislature today, said that decisions were being taken on ad-hoc basis without any firm development model and long-term plan.
There were avoidable delays in acquiring the land, while in some cases excess land was acquired which lay unused, it noted.
MADC was set up in August 2002 to plan, construct, operate and maintain airports. The government entrusted the company the task of developing three 'greenfield' and six 'brownfield' airports, and a heliport at Gadchiroli.
The greenfield airports were to come up at Pune, Shirdi, Solapur, while brownfield airports were to be developed at Amravati, Chandrapur, Dhule, Karad, Nagpur and Phaltan.
However, CAG pointed out, development of airports was hit by hurdles.

More From This Section

The site for airport at Pune has not been finalised due to restrictions imposed by the Indian Air Force (which has an air base there), natural obstructions and opposition from land owners.
The pre-feasibility study expressed concerns regarding commercial viability of Karad airport in western Maharashtra, as the location is close (70 km) to the existing airport at Kolhapur.
Dhule airport was also found to be not viable, while feasibility study of Chandrapur airport in Vidarbha indicated that the extension of runway of the existing airport was not possible.
It was decided that a new airport should be developed in Chandrapur, but the site was yet to be finalised.
As to the airport at Phaltan, MADC had not made any plans yet, the CAG said.
Grants given by the state government for development of airports were lying unused, thus "blocking up" the public money, it said.
MADC should evolve a long-term plan for timely development and expansion of these projects and assess land requirement in advance so as to avoid delays and "idling" of funds, the CAG said.