In the absence of gates, the dam was overflowing for the last two months and the installation of spillways piers will take the dam to its full height of 138 meters, an official release said here today.
NCA, at the behest of Ministry of Water Resources, River Development and Ganga Rejuvenation, has given permission to SSNL to carry out Phase-I proposal comprising construction of piers, overhead bridge and installation of gates in open or raised position at Sardar Sarovar project as per the approved design.
In the absence of NCA's permission, the construction work at the dam site in Kevadia colony came to stand still.
NCA, on June 12, gave its approval to Gujarat for raising the height of the Sardar Sarovar Dam to 138.68 metres from the present 121.92 metres, in a decision that will benefit parched regions of the state.