A bench headed by Justice U D Salvi issued notices to the Union Ministry of Environment, Forests and Climate Change, Uttar Pradesh government, Ghaziabad Development Authority and others while seeking their replies by July 15.
The directions came while hearing a petition filed by Ghaziabad resident Sushil Raghav who has contended that the construction work started in this area without any permission from State Environment Impact Assessment Authority as required under EIA notification 2006.
Raghav claims that the land originally belonged to Arthala gram sabha but was handed over to Ghaziabad Municipal Corporation in 1990. Later, in 1993-94, the then district magistrate notified it as a bird sanctuary, making the district forest department its custodian in 1995.
The plea, filed through advocate Rahul Choudhary, said that as per the information available on the website of State Environment Impact Assessment Authority and MoEF, no Environmental Clearance has been granted for any kind of activity on the bird sanctuary which is home to many migratory birds.