A bench headed by Justice Jawad Rahim imposed an environment compensation of Rs three lakh each on the builders after perusing the inspection report filed by the Delhi Pollution Control Committee (DPCC).
During the proceedings, DPCC told the tribunal that some of the builders have removed the deficiencies pointed out to them and rectified the problem in their rainwater harvesting structure.
"We are satisfied that as of now the noticees appear to be compliant unit. However for the violation they have committed, compensation has to be imposed. Thus, the amount of compensation payable by the noticees...shall be Rs 3 lakh each and it shall be deposited within three weeks," the bench said.
Taking several hospitals, malls and hotels here to task for not complying with its orders on rainwater harvesting, the NGT had last year imposed fines and issued warrants to many of them for not installing these systems.
The green panel was hearing a plea by environmentalist Vikrant Kumar Tongad who had sought directions to Delhi Metro Rail Corporation to "install proper rainwater harvesting system" on all its existing, proposed and under-construction metro stations, tracks and depots.