The company had reported a profit of Rs 311.77 crore in the same period in the previous financial year, NHPC said in a regulatory filing to the stock exchanges.
Total income from operations increased to Rs 1,144.63 crore from Rs 1,010.37 crore a year earlier.
NHPC's total expenses rose to Rs 815.20 crore from Rs 640.65 crore and finance costs climbed to Rs 151.15 crore from Rs 98.92 crore.
NHPC bought back 123 crore equity shares at Rs 19.25 each in the offer that started on November 29 and closed on December 12. The company purchased 110.7 crore shares worth more than Rs 2,130 crore from the government, equivalent to 90 per cent of the buyback.
Also Read
The government's stake in NHPC was reduced to 85.96 per cent from 86.36 per cent.
NHPC has a generation capacity of 5,702 MW from 17 hydro-electric stations in the country. Seven plants with a combined capacity of 4,095 MW capacity are under construction.