"Keeping in view the present steel market scenario and also to move on a steady pace, it is decided to undertake the expansion in two phases. In the first phase NINL's capacity will be doubled to 2.2 MTPA," NINL Chairman Ved Prakash told reporters here.
In the second phase, the capacity would be raised up to 5 mtpa at the NINL plant located at Kalinga Nagar in Duburi area of Jajpur district, he said, adding that he met Chief Minister Naveen Patnaik earlier on the day and explained to him about the expansion plans.
Prakash, who is also the CMD of MMTC, said the first phase expansion would be completed around 2020 and second phase by 2024-25.
Dismissing speculation about likelihood of other players picking up stake in NINL, he said despite global recession the company managed to survive and it is up to date on repayment of loans and interest, whereas many other steel plants are facing NPA and on the verge of closing down.