The Comptroller and Auditor General report on KNPP units 1 and 2 was tabled in the Lok Sabha today.
According to the report, the cost of Russian scope in building the plant was nearly USD 1,600 million during initial negotiations between the NPCIL and Russia's Atomstroyexport.
The Russian side made an offer that the cost may decrease if the NPCIL takes up the work of erection and commissioning of Nuclear Steam Supply System (NSSS) and Turbo Generator (TG).
During the final round of negotiations in August 2001, the offer was accepted by NPCIL and the cost of Russian scope was reduced to a fixed price of USD 1,535 million (Rs 7,217 crore).
Also Read
This was to reduce the cost by USD 65 million (Rs 305.50 crore) by cutting down the number of Russian personnel at the project's site in Tamil Nadu.
A CAG audit found that NPCIL incurred expenditure of Rs 1,012.37 crore towards erection and commissioning of NSSS and TG, as against the Rs 305.50 crore previously estimated.
In its reply to the CAG, NPCIL on June 28 this year said the erection and commissioning of NSSS and TG was shifted to the Indian side in order to learn the technology, which is "generally not parted by foreign vendors", and thus "cannot be quantified in monetary terms".
The unit 1 of the KKNPP started commercial operations in December 2014 and unit 2 in March this year. They were built at a cost of Rs 22,462 core.