These include green-field ferro-chrome plant of Tata Steel set up with an investment of around Rs 542 crore and high-titanium slag of Saraf Agency with an investment of Rs 350 crore.
The 55,000 tonne per annum ferro-chrome project, billed as the first greenfield project with state-of-the-art pollution control equipment and technology such as effluent technology and sewage treatment plant, started its production.
The water requirement for the plant will be met through rainwater harvesting.
The ferro-chrome one is the anchor project of Tata Steel's Industrial Park at Gopalpur while several companies have evinced keen interest in investing in the park, Managing Director, Tata Steel (India and SEA) TV Narendran said.
More From This Section
The plant was set up at a cost of Rs 542 crore.
Tata Steel had acquired around 2,970 acres in the area in 1996 for setting up of a mega steel plant. But the company changed its decision and decided to set up the Industrial Park that now includes the SEZ.
As many as 656 core families and 989 extended families of at least five villages near Gopalpur had been displaced in 1996 while people of around 17 villages were affected.
"The plant has already started operation on experimental basis and it will be stabilised soon," said a senior officer of the company.