"Consequent upon testing and commissioning, 200 mw capacity (4X50 MW) of NP Kunta Ultra Mega Solar Power Project Stage-I at Anantapuram is declared on commercial operation w.E.F. 00:00 Hrs of May 9, 2016," NTPC said in a BSE filing.
State-run power producer NTPC added 2,255 MW capacity last fiscal.
In the 12th Five-Year Plan (2012-17), NTPC added 9,639 MW, making it the company's highest capacity addition in a Plan period.
In the last Plan period, it added 9,610 MW capacity. The company has set a target of adding 11,900 MW capacity during the current Plan period ending in 2016-17.