They said that the unit, which was generating 240 MW and had so far supplied 5.3 crore units of power to the Southern grid, would be taken up for maintenance by Indian and Russian specialists.
The maintenance would enable the unit generate power on a regular basis, they said.
On August 29, the second unit was test synchronised with the southern power grid, marking generation of electricity from the unit and its supply to the grid.
"The power level will be increased in phases to 50, then 75 and 90 per cent and later to 100 per cent full power after obtaining necessary regulatory clearances," he had said in a statement.
Also Read
KNPP-2 attained first criticality on July 10 this year and subsequently various reactor physics experiments were carried out at low power.
It was done under supervision of experts from Atomic Energy Regulatory Board, NPCIL and Russian specialists.
KNPP has been set up using Russian VVER type reactors based on enriched uranium.
Pressurised Water Reactor VVER-1000 had gone critical in July 2014 and the commercial operations started from December 31 the same year, with the unit coming to the aid of the then power starved Tamil Nadu.