Don’t miss the latest developments in business and finance.

Power generation resumes in thermal plant

Image
Press Trust of India Tuticorin (TN)
Last Updated : Apr 17 2013 | 12:30 PM IST
Power generation from the two units of the thermal power plant here resumed after rectifying the technical problem, officials said.
The boilers of the two units, first and third, of the Tuticorin Thermal Power Station (TTPS) with a capacity to generate 210 MW each, had developed technical snag on Monday.
The two units started generating power from last night after the engineers rectified the defects, the sources said, adding, all the five units were working "perfectly" now.

More From This Section

First Published: Apr 17 2013 | 12:30 PM IST

Next Story