With this, the coal supply to PSPCL plants will be fully restored.
"With the efforts of management and officers of PSPCL, the issue of coal supply has been resolved with Panem and normal coal supply has been assured by the firm from today," Punjab State Power Corporation Ltd (PSPCL) Chairman and Managing Director K D Chaudhri said today.
Chaudhri said that PSPCL had agreed to pay Rs 6 crore interest bearing advance on daily basis and interest bearing Rs 100 per metric tonne to Panem Coal Mines.
Panem Coal Mines had suspended coal supply to PSPCL's three thermal power plants, Ropar, Bathinda and Lehra Mohabbat on April 11, which led to "less generation" of power, forcing the PSPCL to buy short term power at "higher" rate and imposing "unscheduled" power cuts.
More From This Section
PSPCL had said in its petition that it could generate only 800 MW of power at its three own power plants at Ropar, Bathinda and Lehra Mohabbat because of suspension of coal supply by Panem Coal Mines.
However, later it had partially restored coal supply.
Panem Coal Mines supplies 7 million tonne of coal to PSPCL's thermal units, which accounts for 60 per cent of power utility's requirements.
Chaudhri claimed that three thermal units of PSPCL would now get normal supply of coal which is 6 coal rakes per day.
PSEB Engineers Association had even sought probe from Punjab government into allegedly giving "undue benefits" to coal supplier by power utility PSPCL, saying it would force energy consumers to pay more for electricity in the state.
He said, "the fact is that PSPCL has been maintaining uninterrupted power supply to all category of consumers.