"My focus is to complete the ongoing projects and not to announce any new one. We have 34 different projects going on in the northeast with an estimated total cost of around Rs 54,000 crore," Railways Minister Sadananda Gowda said today.
"The remaining work of the projects will be completed in the next 5-6 years and funds will be allotted in coming years," he added.
According to Northeast Frontier Railway about Rs 20,000 crore have already been spent for these projects as on March 31, 2014.
The total ongoing projects of laying new tracks and gauge conversion is 4,517 km as on April 1 this year, of which only 1,889 km have been commissioned.
Also Read
Gowda said the Railway Budget for 2014-15 has allotted Rs 5,400 crore for carrying out the ongoing projects and it was 54 per cent higher than the previous year.
"Our target is to complete construction of 450 km this year compared to 310 km in last year," he said.
"In the next five years, all the state capitals in the northeast will have rail connections," he said adding acquisition is on to restart rail link between Agartala and Akhaura in Bangladesh.