The Union Cabinet approved the revised cost estimates for setting up eight New IITs at Bhubaneswar, Gandhinagar, Hyderabad, Indore, Jodhpur, Mandi, Patna and Ropar.
The revised estimate is Rs 13,990 crore to be spent over a period of 11 years from 2008-09 to 2018-19.
The original project cost was Rs 6,080 crore. The increase in expenditure due to escalation in both time and cost overrun is Rs 7,910 crore, an official statement said.
The direct beneficiaries in terms of numbers would be about 12,880 students. However, indirectly the new IITs would be expected to bring about quantitative and quality growth in the areas of research, publication of books and research papers, registered patents, trademarks, designs and quality improvement programmes.
Also Read
"These institutes would also meet the emerging needs of the industry and the economy as a whole, for skilled technical manpower is expected to be met from the talent pool of trained personnel of these new institutions...These institutions will provide research and development atmosphere with sizable infrastructure...," the statement said.
In another decision, the Cabinet also gave ex post facto approval for extension of Addendum IX for the period April 1, 2011 to March 31, 2016 and renewal of MoU between Government of India and Shastri Indo-Canadian Institute (SlCI) by way of signing supplementary Addendum X to the agreement signed in November, 1968.
The approval would pave the way for Shastri Research Fellowship and Mobility Programme, doctoral and post-doctoral research and publication of research materials, documents and reports.