The railways have started to inform passengers about the status of affected trains through SMS. Passengers with confirmed tickets of a cancelled train would get a message about cancellation of their train on their mobile phones.
It will take about 35 days to restore the normalcy on the section as the RRI room has been gutted, Railway Board Member (Traffic) Ajay Shukla said here today after returning from Itarsi.
"Since Itarsi junction is centrally located, trains coming from all directions are being disrupted. Now the operation is managed manually, as a result many trains are running late, affecting the punctuality," Shukla said.
Many trains were cancelled while some have to be diverted. Services of about 141 passenger trains were affected and about 50 freight trains were diverted due to the fire, causing loss to the public transporter.
Also Read
According to a senior Railway Ministry official, since it will take more than a month to restore normalcy, it is estimated that railways will suffer loss of about Rs 130 crore during this period.
RRI is a system by which all the signals and the points or crossings which are used for changing of routes at junction station are operated centrally from a cabin through electrical devices.
Divisional officers are camping at the site to manage the situation.