The government also assured a division bench headed by Justice Abhay Oka it would conduct a special drive to check vehicles for the purpose of issuing fitness certificate.
The government pleader informed the bench that process had been initiated to provide land for tracks at 35 RTOs.
Three more RTOs-- Baramati, Osmanabad and Satara-- would get land for this purpose within two weeks, the court was informed.
In August, the high court had warned the government to follow its earlier order of constructing 250-metre road track at all the RTOs in the state to test four-wheeler for issuance of fitness certificates or face contempt action.
Also Read
The court had asked the government to give an assurance it would construct the track at all the RTOs. The assurance was given today by the Maharashtra government.
The state government had filed an application earlier
stating it would not be possible to construct 250-metre track at all the RTOs citing "unavailability" of land.
Two years back, the high court had restrained four RTOs -- Latur, Nashik, Pune and Mumbai Central-- from issuing fitness certificates, saying they were not fully equipped to conduct tests required under the Motor Vehicles Act and also they had not complied with its order of February 28, 2014.
The high court had then passed orders asking all the 49 RTOs to maintain necessary infrastructure to carry out the tests.
The RTOs were warned they would be restrained from issuing fitness certificates in case of non-compliance.
It is also mandatory under the Act to make the headlight beam adjustment with a machine so that the light does not fall on the face of oncoming drivers. Even this condition was not complied with by the RTOs, the PIL alleged.