A forest bench headed by Justice J S Khehar, expressing unhappiness over delay, said this will be the last chance to the ministry and if the task is not completed the Secretary, MoEF will be personally held responsible.
The apex court while allowing operations at the functional units in the SEZ had in January asked the environment ministry to take decisions in three months. The time was extended by 8 weeks but today the court was informed that decisions are yet not taken.
Earlier, on January 27, the apex court had granted conditional permission to industrial units within the Adani Port Special Economic Zone (APSEZ) in Gujarat to resume operations asking them to desist from carrying out any further construction until environmental clearance from the Centre.
The apex court had retained the high court order which had said that the Centre has to decide within 30 days whether the environmental clearance should be granted.