Replying to a calling attention in this regard in the state assembly, Minister for Ports K Babu said the last date for Request for Qualification of the global tender floated was February 4 and government expected to complete the process by August.
"Government wants to start the work of the port by this year." The Environment and Forest Ministry had given its clearance last week, he said.
Government envisages to implement the project under 'Landlord' model and "there is no change in this", Babu said replying to the contention of Kodiyeri Balakrishnan (CPI-M) that it was planning to implement the scheme under PPP model and that would again result in delay in executing the work.
Government has re-structured the project after study of Project Re-structuring Operation report. The cost would come to around Rs 3,640 crore as per the estimate in 2012. However, with global tender floated now, difference in the dollar rate would also be reflected, he said.
More From This Section
As per the new master plan of the project, a mother vessel with 18,000 TEU capacity would be able to berth at the port. In the earlier plan, capacity of the port was to berth vessel with 9000 TEU, he said.
The Consortium under State Bank of Travancore has agreed to make available funds for the project once it gets environment clearance.
Besides this, the project also would get Rs 500 crore from Navy and Coast Guard, he said and asked the CPI-M-led LDF to co-operate with government in executing it.
Babu also asked the LDF not to create any confusion over the project especially at a time when the global tender for private partner has been floated.
He asked government to take steps for the project's speedy implementation.