"We had pegged the estimated daily traffic flow to be 1,45,000 PCU (passenger car unit - a unit of traffic flow measurement), but only 45,000 PCU is recorded every day," Director (Corporate Development and Governance) of Second Vivekananda Bridge Tollway Pvt Ltd, Lala K Roy told reporters here.
"The daily traffic flow is far less than the estimated target," he said.
The low traffic movement can be attributed to the lack of heavy industries in the state, he said.
"Now, we are making a very small margin of profit but we hope to better it in the next two-three years time, when there will be expected traffic growth," he said.
Also Read
The official said out of the Rs 673-crore total investment for the bridge, Rs 250 crore was pumped through the FDI route, making it the "largest FDI in Eastern India in transport sector".
To a question, Roy said there was encroachment under the bridge viaduct, with bus and truck stands coming up in the Dakshineswar stretch, which may cause damage to the adjacent pillars. "But you have to consider the issue from a human and practical point of view."
The 6.1-km, six-lane bridge connects major industrial areas and emerging townships.