Babu told reporters today that currently export and import operations were running smoothly after restoration works were underway.
He said the offshore terminal tanker for crude import was damaged and suffered an estimated loss of Rs 100 to 120 crore. A team of experts from Nigeria-based company ASCON will visit the port to restore the facility.
However, single point mooring facility was intact and crude required for Hindustan Petroleum Corporation Ltd (HPCL) here is being imported through it, he said, adding, the port is facing no hindrance in importing crude oil to the HPCL refinery.
There is no insurance coverage for the port installations and the port has to raise funds on its own to take up the necessary repair works, he said.
Ongoing projects worth Rs 3,000 crore remained unaffected by the cyclone, Babu said.
Operation at the port was affected for five days after the cyclone had hit Andhra coast on October 12 and had caused severe damage to Visakhapatnam city.