This observation was made by a World Bank team led by its task team leader S Poddipireddy during a meeting with Punjab Chief Minister Parkash Singh Badal, said an official release.
The meeting was held to apprise the World Bank team about the progress made under the ongoing World Bank-aided PRWSS project here, it said.
The Rs 1,280 crore PRWSS project has exceeded the implementation targets under water supply component by 127 per cent and providing water connections to each household in the village.
More than 961 villages implemented under the project have already achieved 100 per cent connectivity and each household in these villages was drawing high quality water from its own tap in the house.
Gram Panchayat Water and Sanitation Committees (GPWSCs) of more than 50 per cent (2,083) villages were operating and maintaining this scheme on sustainable basis without any financial assistance from the government and have generated sufficient funds in their Operation & Maintenance (O&M) accounts varying from Rs 1 lakh to 10 lakh, he said.