Don’t miss the latest developments in business and finance.

Bullet Train Project

Railways Minister Ashwini Vaishnaw on Saturday inspected a track slab manufacturing factory for the Mumbai-Ahmedabad bullet train project near Surat in Gujarat. Vaishnaw said all the equipment at the factory in Kim was initially brought from Japan before their manufacturing was started in India, which will be beneficial for upcoming construction projects. "This factory at Kim is the largest in India and one of the largest track slab factories in the world. The workers have a very high skill level here. Those engaged in validation, test and check also have a very high skill level, and they have maintained very good standards," Vaishnaw told mediapersons after the visit. He said the experience in manufacturing equipment in India after initially bringing them from Japan will benefit future construction projects. The track slab manufacturing factory, set up near Surat to support India's first bullet train project, is designed to produce high-capacity ballast-less track slabs using ...

Updated On: 30 Nov 2024 | 5:46 PM IST

The National High Speed Rail Corporation Limited (NHSRCL) on Friday said it has received more than 35,000 MT of rails and four sets of track construction machinery for the Ahmedabad-Mumbai bullet train project. The process of flash-butt welding of rails to form 200-meter-long panels has started on the viaduct as track construction is underway near Surat and Anand cities in Gujarat, the NHSRCL said in a release. The 508 km high-speed corridor is being constructed between Ahmedabad and Mumbai. The bullet train project will have a J-Slab track system based on the Japanese Shinkansen track system. This is the first time the system will be used in India, it said. The process of track installation is mechanised with cutting-edge machinery, specially designed and manufactured as per Japanese specifications, it was stated. As per the release, the NHSRCL has received more than 35,000 MT of rails and four sets of track construction machinery for the project. The fleet of machines includes

Updated On: 13 Sep 2024 | 4:32 PM IST

As Indian Railways aims to develop trains capable of running at 250 km per hour, here is a list of countries known for their expertise in manufacturing high-speed trains

Updated On: 07 Jun 2024 | 10:35 AM IST

The indigenous bullet train will outpace the speed of any existing trains within the Indian Railways network

Updated On: 17 Apr 2024 | 11:34 AM IST

Railway Minister Ashwini Vaishnaw Friday said the Mumbai-Ahmedabad bullet train project will prove to be a corridor of economic prosperity, transforming towns and cities along the route and becoming a learning experience for future initiatives. Vaishnaw triggered a blast to build a shaft at Vikhroli to lower tunnel boring machines (TBM) for the construction of the 21-km underground tunnel, which is considered to be a technological marvel of India's first bullet train project. "Trains will zip through the tunnel at a maximum speed of up to 320 km. Constructing it without disturbing the tall buildings in the area is a challenge," the railway minister said. The shaft at the Vikhroli site of the National High Speed Rail Corridor is one among the four to be built for the entire 21-km-long underground stretch of the Mumbai-Ahmedabad Bullet Train Project. The shaft-2 will be used to launch two TBMs -- one towards the Bandra-Kurla Complex (BKC) station's east end and the other towards Sawl

Updated On: 23 Feb 2024 | 7:57 PM IST

The Mumbai-Ahmedabad bullet train project will help improve the partnership between Gujarat and Mumbai at the social level, Gujarat Chief Minister Bhupendra Patel said here on Wednesday. Gujarat and Mumbai are important pillars of the Indian economy, and ongoing infrastructure projects where the two have partnered will help both, he said. Speaking at an investor roadshow here ahead of the tenth 'Vibrant Gujarat' summit here, Patel said while Mumbai is the financial capital of the country, Gujarat has become the most preferred investment destination. "The bullet train project will help infrastructure development and economic activities, but also improve the partnership on the social level," Patel said in comments that come amid some instances showing a lack of warmth between Marathi and Gujarati-speaking communities in the financial capital. Recently, workers from the Uddhav Thackeray faction of the Shiv Sena allegedly vandalised Gujarati posters in suburban Ghatkopar, which has a .

Updated On: 11 Oct 2023 | 5:14 PM IST

The National High Speed Rail Corporation Ltd (NHSRCL) on Thursday said it has awarded contract for the Mumbai-Ahmedabad Bullet train project's 'last civil package' of a 135-kilometre section. The Bullet train corridor is divided into 28 contract packages, of which 11 are 'civil packages'. The works in the 135 km section between Shilphata in Thane district and Zaroli village on the Maharashtra-Gujarat border included seven tunnels and the longest bridge of 2 km over the Vaitarna river in Maharashtra besides the construction of Thane, Virar and Boisar stations, the corporation said in a statement. NHSRCL has already awarded contracts for the construction of Mumbai (BKC) station and 21 km of tunnels including a 7 km undersea tunnel works in Maharashtra. With this last tender, all civil contracts for the Mumbai -Ahmedabad High Speed Rail corridor have been awarded, the release said. "This also marks the award of all the 11 civil packages of 508 km long MAHSR corridor, comprising 465

Updated On: 21 Jul 2023 | 7:54 AM IST

Hindustan Construction Company Ltd (HCC) in a joint venture with Megha Engineering & Infrastructures Ltd (MEIL) has bagged a Rs 3,681 crore project for construction of a bullet train station, a statement said on Tuesday. The contract was awarded by the National High-Speed Rail Corporation Ltd (NHSRCL) for the construction of the Bandra Kurla Complex Station of the 508.17 km-long Mumbai-Ahmedabad high-speed rail. The Bandra Kurla Complex bullet train station will have six platforms, and each platform is approximately 414 metres, sufficient to accommodate a 16-coach bullet train. The station will have connectivity with the metro and road transport, HCC said in a statement. This station is the only underground station on the Mumbai-Ahmedabad high-speed rail corridor, and it is planned at a depth of about 24 metres below the ground level. The station will have a total of three floors. On Tuesday, shares of the company settled 4.33 per higher at Rs 14.95 apiece on the BSE.

Updated On: 14 Mar 2023 | 10:35 PM IST

The state government, in October last year, told the court that the Ahmedabad-Mumbai high-speed rail corridor project is a priority project for the Government of India

Updated On: 09 Feb 2023 | 8:20 PM IST

Firm in partnership with Hindustan Construction Corp bids Rs 3,700 crore to build underground station

Updated On: 30 Dec 2022 | 12:38 AM IST

The fresh TMT bars are 9 metres in length and 16 mm in diameter. These were produced at the plant's modern Bar and Rod Mill, which has so far supplied more than 3,000 TMT bars

Updated On: 24 Dec 2022 | 12:46 AM IST

Work on the railways' ambitious bullet train project between Mumbai and Ahmedabad has gained momentum, with the ministry claiming on Monday that more than 98 per cent of the land has been acquired for the project in Maharashtra. Piers have been erected for a distance of more than 118 kilometres, girders are being launched and the work on the construction of bullet train stations has also started, the railway ministry said. With the change of government in Maharashtra, the pain points in the project in terms of forest clearances and land acquisition seem to have been overcome. In a series of tweets, the ministry claimed that while 98.22 per cent land has been acquired in Maharashtra, in Gujarat, 98.87 per cent land has been acquired and in Dadra and Nagar Haveli, 100 per cent of the land has been acquired for the project. The physical progress till November 23 was 24.1 per cent, the ministry said, adding that while almost 30 per cent of the work has been completed in Gujarat, in ...

Updated On: 20 Dec 2022 | 12:19 AM IST

Larsen and Toubro (L&T) says it has bagged another 'large' order in the proposed Mumbai-Ahmedabad bullet train project from National High-Speed Rail Corporation

Updated On: 05 Dec 2022 | 11:19 PM IST

Survey work is going on to start bullet train services here, Rail Minister Ashwini Vaishnaw said on Saturday. The proposed alignment of the high-speed rail corridor will pass through Greater Noida, Agra, Lucknow, Prayagraj and Varanasi, he said. Speaking on the first bullet train project between Mumbai and Ahmedabad, Vaishnaw said, "New things are being learnt through this (project). As this project develops, there will be more development. "More bullet train corridors will be built in the country. Survey work is going on in Varanasi to start a bullet train." Vaishnaw, who is visiting Varanasi, also inspected Kashi station and Rajghat bridge. Kashi station in Varanasi district will be developed at a cost of Rs 350 crore to boost economic activity. Its design should be done keeping in mind Kashi's religious and temple culture, Vaishnaw told reporters. Plans are also afoot to connect Kashi station with air and water routes and its design is being worked on, he said. Once the desig

Updated On: 05 Nov 2022 | 3:58 PM IST

National High Speed Railway Corporation Limited (NHSRCL) has invited bids for the construction of a 21-km-long tunnel, seven km of which will be under the sea, for the Mumbai-Ahmedabad High Speed Rail Corridor. The work on the corridor has gained momentum after the change in government in Maharashtra, with tenders, which were previously floated and withdrawn, being renewed again, sources said. Considered the highlight of the project, the tunnel will be built between the underground station at Bandra-Kurla Complex and Shilphata in Thane district of Maharashtra. The tunnel will be built using tunnel boring machine and the New Austrian Tunneling Method (NATM), according to the tender document. The seven-km undersea tunnel at Thane Creek will be the first undersea tunnel to come up in the country. In November last year, NHSRCL had invited bids for underground tunnelling works for the project. But it was cancelled this year with officials citing "administrative reasons". In 2019, NHSR

Updated On: 23 Sep 2022 | 6:49 PM IST

Maharashtra Chief Minister Eknath Shinde has directed officials to complete land acquisition for the Mumbai-Ahmedabad bullet train project and disburse compensation to affected people by September 30, the state government said on Tuesday. The Mumbai-Ahmedabad high speed rail corridor is a flagship infrastructure project of the Narendra Modi government that seeks to improve connectivity between the country's financial capital and the commercial hub of Gujarat. The multi-crore project, primarily the land acquisition in Maharashtra, hit hurdle after the Uddhav Thackeray-led Maha Vikas Aghadi (MVA) government took charge in November 2019. After a change of government in the state in June this year, the land acquisition process for the project is being expedited. "CM, Shri @mieknathshinde has directed all officers to complete the land acquisition for the Mumbai-Ahmedabad high speed bullet train project & disburse compensation to affected families by September 30," the Maharashtra ...

Updated On: 30 Aug 2022 | 9:55 PM IST

The estimated cost of the Mumbai-Ahmedabad bullet train project is Rs 1,10,000 crore, out of which Rs 88,000 crore are being funded by the Japan International Cooperation Agency

Updated On: 14 Jul 2022 | 3:53 PM IST

The first phase of the Ahmedabad-Mumbai bullet train project, a 61-km stretch between Surat and Bilimora in Gujarat, is likely to be operational only in 2026

Updated On: 08 Jun 2022 | 2:13 PM IST

Contract manufacturing startup Zetwerk Manufacturing Businesses has bagged an order worth Rs 126.55 crore from L&T for the Mumbai-Ahmedabad (MAHSR) bullet train project, the company said on Thursday. The startup will supply 10,000 metric tonne (MT) fabricated girders to support the load-bearing capacity of the steel bridges that Larsen & Toubro is fabricating for laying the bullet train rail corridor. "Zetwerk Manufacturing Businesses has been awarded a Letter of Intent (LoI) for an order worth Rs 126.55 crore by L&T Ltd for the Mumbai-Ahmedabad (MAHSR) Bullet Train project," the start-up said in a statement. As per the LoI, the MAHSR Bullet Train project is being executed by the National High-Speed Rail Corporation Ltd. "Zetwerk is proud to associate with the Bullet Train Project and will strive to deliver its commitment on time in full. India is on the cusp of a major manufacturing revolution and we are honoured to be able to play an active role in bolstering these ...

Updated On: 21 Apr 2022 | 1:38 PM IST