The order placed by the public establishment of electricity for generation and transmission (PEEGT) - scheduled for execution in 33 months - includes manufacturing supply and commissioning of main plant and balance of plant (BoP) equipment besides Controls & Instrumentation (C&I).
Currently the company has a total physical export turnover of Rs 1,132 crore and planning a six fold increase in it by the end of 2012.
BHEL has a present manufacturing capacity of about 9,000 mw and plans to ramp it up to 15,000 mw by the end of the current plan period (2007-2012).