State-owned Gas Authority of India Limited (GAIL) expects work on the Dhabol-Bangalore gas pipeline project to be completed by March 2012, the company’s CMD B C Tripathi said today.
“The prestigious Rs 5,400 crore project would also lead to generation of about 8,000 Mw of power using gas in Karnataka,” he told reporters after calling on Chief Minister B S Yeddyurappa to brief him on the progress of the work.
The pipeline would pass through 11 districts, ensuring gas supply to consumers, Tripathi said.
GAIL has completed the route survey for the 1,400 Km gas pipeline project for supplying natural gas to Karnataka. GAIL has completed the route survey of the total length of the pipeline network and the tendering process for line pipe procurement will start shortly.