Business Standard

Monday, December 23, 2024 | 11:52 PM ISTEN Hindi

Notification Icon
userprofile IconSearch

Kerala govt to raise Rs 400 cr for Adani Ports as part of Vizhinjam pact

Kerala will have to provide Adani Ports Rs 400 crore when 30 per cent of the breakwater is completed and they have been knocking on the doors of the government for a while

Adani Ports, APSEZ

Photo: Bloomberg

IANS Thiruvananthapuram

As part of the agreement between the Kerala government and Adani Ports, the former will now have to give Rs 400 crore to the latter as the construction of the breakwater at the upcoming Vizhinjam port is going forward.

According to the agreement between the two, Kerala will have to provide Adani Ports Rs 400 crore when 30 per cent of the breakwater is completed and they have been knocking on the doors of the government for a while.

The state government has been caught in a debt trap and the financial position has been in tatters and hence they are unable to honour the commitment to the port builder. With time running out, the Pinarayi Vijayan government has now decided to take a loan of Rs 400 crore from HUDCO.

 

The Vizhinjam port has been a dream project of successive governments and was finally cleared by the then Oommen Chandy government (2011-16) and Adani Ports was the lone bidder for the project.

The work began on December 5, 2015.

Gautam Adani had then announced that the first ship will berth there on September 1, 2018, in a record time of less than 1,000 days, but due to various reasons things went haywire. State Ports Minister Ahamed Devarkovil has now said that the first ship will berth in March 2023 and the first phase of the port will be commissioned in 2023.

The project first stalled in 2017 after cyclone Ockhi hit the construction site and a portion of the constructed breakwater was washed away and since then the shortage of limestone, the most important raw material for the project, caused another delay.

The total cost of the port project is Rs 7,525 crore and the state government has contributed 500 acres of land.

According to the plan, once completed, this would be one of India's deepest ports and 80 per cent of the country's cargo trans-shipments will go through here.

Adani Ports, which was the lone bidder for the project, had sought a Rs 1,635 crore grant for the construction purposes.

According to the agreement, Adani will operate the port for 40 years, extendable by 20 more years, while the state government will get a portion of the revenue from the port after 15 years.

--IANS

sg/dpb

(Only the headline and picture of this report may have been reworked by the Business Standard staff; the rest of the content is auto-generated from a syndicated feed.)

Don't miss the most important news and views of the day. Get them on our Telegram channel

First Published: Feb 13 2023 | 1:07 PM IST

Explore News