Hyderabad-based KNR Constructions Limited has completed the work on 97.221 km of road project on National Highway (NH) 13 in the Bijapur-Hungund section in 582 days against the scheduled duration of 910 days, 11 months ahead of time.
The achievement also includes construction of an 810 m dual carriageway bridge over river Krishna on National Highway 13 (recently changed to NH-50) near Almatti in a record time of 11 months and 16 days, a company release said here on Wednesday.