Tuesday, March 04, 2025 | 11:18 PM ISTहिंदी में पढें
Business Standard
Notification Icon
userprofile IconSearch

L&T wins Rs 844 cr order from NPCIL

Image

BS Reporter Mumbai

Larsen & Toubro’s (L&T) Infrastructure Operating Company – a part of its Construction Division (ECC), has secured a Rs. 844 crore from Nuclear Power Corporation of India Limited (NPCIL) for construction of the main plant civil works of reactor 3&4 at Kakrapar Atomic Power Project, Tapi (Gujarat).

This is the country’s first 700 MW Pressurized Heavy Water Reactor (PHWR) plant being indigenously developed by NPCIL, L&T said in a statement.

The scope of work involves construction of reactor building, auxiliary buildings, waste management and exhaust ventilation building, heavy water upgrading plant, fabrication & erection of structural steel works involving civil, structural and architectural works. The project is to be completed in 49 months.

 

Don't miss the most important news and views of the day. Get them on our Telegram channel

First Published: Dec 08 2009 | 11:34 AM IST

Explore News