The actual date of completion for the dry dock project at the Cochin Shipyard Ltd has been revised to December 2022, owing to various factors, the shipbuilder said on Monday.
"The actual completion date of (setting up of dry dock at the existing premises of CSL) has been revised to December 2022, due to various factors, the major contributor being the Covid-19 pandemic," CSL said in a regulatory filing.
The lockdowns due to the pandemic disrupted the material supply and labour availability, which resulted in extremely low productivity, it said.
The company said the construction work by Larsen & Toubro