The Railways' ambitious infrastructure project -- the Dedicated Freight Corridor-- has been delayed by six months, Railway Board Chairman VK Yadav said Thursday, attributing the delay to the coronavirus crisis that led to workers returning to their hometowns.
The Rs 81,000 crore Dedicated Freight Corridor, the Railways' single-largest developmental project currently underway, was scheduled to be completed by December 2021. It consists of the Eastern DFC, a 1,839-km freight line from Ludhiana in Punjab to Dankuni near Kolkata, West Bengal, and the 1483-km WDFC or western corridor connecting India's capital Delhi and its economic hub Mumbai.
We suffered a