In a move that would beef up power supply to Delhi, Power Grid Corporation (PGCIL) said it would invest around Rs 1,000 crore to create an alternative power corridor.
|
|
The 400 Kv parallel corridor from Rihand to Ballabgarh is expected to be commissioned by the end of 2004.
|
|
"The corporation will invest around Rs 1,000 crore for setting up an alternative power highway to bring power to the Capital,' PGCIL executive director DG Sohony said here today.
|
|
This would not only reduce dependence on the existing Rihand-Dadri line but would also provide for evacuation of additional power in the future to meet the growing power requirements, Sohony said.
|
|
The project, currently under implementation, involves setting up of power line for carrying direct current from Rihand to Ballabgarh via Allahabad and Mainpuri with a capacity of nearly 1,000 Mw.
|
|
Outlining the steps the corporation was taking to remove bottlenecks on the existing lines, Sohoni said PGCIL had decided to replace insulators besides cleaning of the same.
|
|
To protect transmission towers, the corporation has also decided to install bird guards. Trippings along the Rihand-Dadri line have been blamed for last winter's power crisis.
|
|
The current inter-regional power transfer capacity of 8,000 Mw is proposed to be enhanced to 30,000 Mw by 2012, company officials said.
|
|
The corporation was planning to set up an additional 60,000 km of transmission network by 2012 at an estimated investment of Rs 70,523 crore.
|
|
Of the proposed investment, the corporation would contribute nearly Rs 50,000 crore and the rest would have to come from the private sector, officials said.
|
|
The transmission network in the northern region is also expected to get a boost with Powerlinks Transmission Ltd, a joint venture between PGCIL and Tata Power, executing the Tala hydel project.
|
|
The project, meant to evacuate power from the 1,020 Mw Tala hydroelectric project in Bhutan, involves setting up of a 1,200 km power transmission line from Siliguri in West Bengal to Mandola in Uttar Pradesh and entails an investment of around Rs 1,200 crore.
|
|
Powerful prospects
- The 400 Kv parallel corridor from Rihand to Ballabgarh is expected to be commissioned by the end of 2004
- This will not only reduce dependence on the existing Rihand-Dadri line but will also provide for evacuation of additional power in the future to meet the growing power requirements
- The current inter-regional power transfer capacity of 8,000 Mw is proposed to be enhanced to 30,000 Mw by 2012
- The corporation was planning to set up an additional 60,000 km of transmission network by 2012 at an estimated investment of Rs 70,523 crore
|
|
|
|