|
Halfway through the year, the corporation today noted that it achieved top ranking in the country among the power generating corporations on various counts.
|
|
For the period April-September, the total thermal generation touched 11,184 million units (mu) with a plant load factor (PLF) of 85.7 per cent, which is the highest in the country.
|
|
The generation too was a record as it exceeded the target of 9,750 mu by 14.7 per cent. Genco also achieved the highest PLF of 90.9 per cent with a gas power generation of 1,086 mu.
|
|
It was only the hydel generation which was hit due to poor inflows. The total hydel generation was only 764 mu against a target of 2,638 mu.
|
|
With the total installed capacity of 6,557 mw, the third highest in the country, APGenco accounted for 12,694 mu of the total system demand of 25,890 mu.
|
|
Briefing media persons, APGenco chairman and managing director J Parthasarathy said all the six units 150 mw each were commissioned a Srisailam Left Bank Power House, a unique fully underground power house in the country.
|
|
Genco had also completed all the works at Alimineti Madhava Reddy Lift Irrigation Scheme at Puttamgadi in Nalgonda district at a cost of Rs 269 crore as against the sanctioned Rs 430.32 crore, thus saving as much as Rs 161 crore, a 37.5 per cent.
|
|
On the mini-hydel power projects, Parthasarathy Genco had nine mini hydro stations with a capacity of 8 mw. He said they produced 12 mu last year and 4 mu so far during the current year.
|
|
Genco would commission another four mini hydro stations with a capacity of 4.15 mw during the current year on the branch canal of Sriram Sagar Project.
|
|
He further informed that as part of capacity addition programme, Genco was planning to construct 1x660 mw unit at VTPS, RPP stage-ii (2x210 mw), and 6x39 mw hydro station at Jurala.
|
|
As part of its anti-pollution efforts, Genco proposes a coal washery at Mahanadi Coal Fields for supply of washed coal to VTPS. It is estimated to cost around Rs 80 crore.
|
|
Due to the remedial measures taken up by Genco at Kinnerasani dam, which supplies water to Kothagudem Thermal Power Station, water was built upto a record full reservoir level of 407 feet.
|
|
With the present storage at 8.4 tmcft, with an additional storage capacity of 2.25 tmcft, Genco is in a position to spare 1 tmcft of water for irrigation in Khariff season.
|
|
The total turnover of Genco was expected to be around Rs 4,000 crore for the current year. It was Rs 2,050 crore for first half-year.
|
|
Parthasarathy added that about Rs 1,893 crore high-cost loans were swapped with low-cost loans, resulting in a saving of Rs 168 crore. Another Rs 1,493 crore is proposed for swapping by the fiscal end, saving an amount of Rs 170 crore. |
|