Cabinet approves National Highways Interconnectivity Improvement Project
The Cabinet Committee on Economic Affairs, chaired by the Prime Minister Shri Narendra Modi, has given its approval for development of 1120 kms of National Highways in the States of Karnataka, Odisha, Bihar, Rajasthan and West Bengal.
The work for development to two lane standards are under Phase-I of the National Highways Interconnectivity Improvement Project (NHIIP) with World Bank assistance.
The revised estimated cost is Rs. 6,461 crore including cost of land acquisition, resettlement and rehabilitation and other pre-construction activities.
The projects are already taken up for implementation and 429 kms has been completed. The civil works are expected to be completed by July, 2019 and maintenance works are expected to be completed by July, 2024.
The project will ensure safe, fast and all weather movement of traffic on the proposed National Highways mostly located in backward regions thereby improving socio economic development.
Background:
The proposal was initially approved for Rs.5,193 crore. The cost has increased due to higher bid prices, and increase in cost of land acquisition, resettlement and rehabilitation and other pre-construction activities.
The work for development to two lane standards are under Phase-I of the National Highways Interconnectivity Improvement Project (NHIIP) with World Bank assistance.
The revised estimated cost is Rs. 6,461 crore including cost of land acquisition, resettlement and rehabilitation and other pre-construction activities.
The projects are already taken up for implementation and 429 kms has been completed. The civil works are expected to be completed by July, 2019 and maintenance works are expected to be completed by July, 2024.
The project will ensure safe, fast and all weather movement of traffic on the proposed National Highways mostly located in backward regions thereby improving socio economic development.
Background:
The proposal was initially approved for Rs.5,193 crore. The cost has increased due to higher bid prices, and increase in cost of land acquisition, resettlement and rehabilitation and other pre-construction activities.