Business Standard

Unrest in Valley adversely affecting road construction by BRO

Image

ANI Srinagar (Jammu and Kashmir) [India]

The ongoing unrest in the Kashmir Valley has adversely affected the Road construction activities undertaken by Border Road Organisation (BRO).

The BRO has suffered loss of working season, loss of more than three months of working season during summers is of serious concern, while endeavours are being made to execute work whenever and wherever possible.

But owing to restrictions on movement of vehicles and persons, desired progress could not be made and as a result many appreciated targets perforce will have to be revised.

Four-laning works on Srinagar-Baramulla-Uri scheduled for completion by July 2016 has been delayed.

Handing over of Road Sinathan Pass- Anantnag to National Highways Authority Of India (NHAI) will be postponed as the pending work on this road will now go beyond the planned PDC of September 2016.

 

In addition, many vehicles/ equipment have been damaged, non-availability of which will directly affect the work efficiency. The most affected locations where delay/ loss of work have been seen are Tangdhar, Anantnag, Kupwara and Bandipur sectors.

Majority of the non-local labours from the Valley have moved out of State for search of their daily livelihood due to continuous disturbance in the state.

The movement and shifting of the material to forward areas have also hampered the work in Ladakh region which will severely impinge on the completion of strategic roads and spending of allotted funds.

Disclaimer: No Business Standard Journalist was involved in creation of this content

Don't miss the most important news and views of the day. Get them on our Telegram channel

First Published: Sep 22 2016 | 7:42 PM IST

Explore News