Business Standard

Board of Borosil Renewables considers revision in cost and commissioning of third furnace

Image

Capital Market

At meeting held on 14 July 2022

The Board of Borosil Renewables at the meeting held on 14 July 2022 noted the revised cost of Rs.688 crore from earlier Rs.600 crore in respect of the Company's third furnace i.e. SG-3 being installed at its manufacturing facility in Bharuch, Gujarat with capacity of 550 Tonnes Per Day (TPD). The Board also took note of the delay in commissioning of the said furnace, as a result of multiple factors including rupee depreciation, exceptional increase in the prices of Commodities, electronic products and ocean freight rates. The SG-3 furnace, which was expected to be commissioned by July 2022, is now expected to be commissioned by October 2022.

Powered by Capital Market - Live News

 

Disclaimer: No Business Standard Journalist was involved in creation of this content

Don't miss the most important news and views of the day. Get them on our Telegram channel

First Published: Jul 14 2022 | 6:21 PM IST

Explore News