Acheives first synchronization of 685 MW unit
GMR Infrastructure announced that the first 685 MW unit of GMR Chhattisgarh Energy's (GCEL) 1370 MW supercritical coal-based thermal power plant at Raikheda in Chhattisgarh's Raipur District has successfully achieved synchronization with the grid on 02 October 2014.GCEL is the GMR Group's first supercritical coal-based thermal power plant. The unit used fuel oil to achieve this first synchronization. The project has been implemented on multiple packages concept by Doosan of Korea. Work on commissioning GCEL's second unit of 685 MW is in progress.