For O&M of Yashwantrao Chavan Expressway & Mumbai Pune section of NH-4
IRB Infrastructure Developers announced that Mhaiskar Infrastructure, wholly owned subsidiary of the Company has now executed concession agreement with MSRDC for the project of Operation & Maintenance of Yashwantrao Chavan Expressway and Mumbai Pune section of NH-4 along with execution of additional works on Mumbai Pune section of NH-4, on DBFOT basis with toll rights in the state of Maharashtra ("the Project").Key highlights of the Project are as under:
- The Project is on DBFOT Pattern;
- Operation & Maintenance of Yashwantrao Chavan Expressway and Mumbai Pune section of NH-4;
- The scope of additional works on Mumbai Pune Section of NH-4 consists of widening from 2 to 4 lanes of 17.38 kms inclusive of elevated road of 1.5 kms length near Dehu Road, 12 kms of service road, 3 Nos. of 3 lane Flyovers, 1 two lane Rail over bridge and widening of existing 8 lanes toll plazas into 12 lanes toll plazas;
Also Read
- The estimated cost of the Project is approximately Rs. 1,687 crore, including Rs. 1,000 crore as Upfront Premium payable to MSRDC in 4 annual installments as prescribed in the bid, commencing from 31 March 2015;
- The concession period for the Project is 8 years 8 months and 2 days commencing from 31 March 2015. The Construction works as mentioned above and payment of Upfront premium installments to MSRDC have to be completed as prescribed in the bid till 10 August 2019;
- The toll collection for the Project will commence from 10 August 2019, resulting into an effective tolling period of 4 years 3 months 22 days only.