The details of project are as follows:
Sl. No. NH No. Section Length Total Capital Cost (Crore) Contractor's name1
21
4-Laning of Nerchowk - Pandoh section
26 KmRs. 1274 crore
M/s KMC Constructions Ltd.
More From This Section
The development of the crucial 26 km long Nerchowk - Pandoh including Pandoh bypass section of the NH-21 will improve the connectivity for travelers from Chandigarh to the valleys of Kullu and Manali. This will improve the transport of the horticulture produce like apples etc. to the markets and also provide better connectivity to local commuters.
The project will have two bypasses (about 8 km long Mandi Bypass and about 5 km long Pandoh Bypass), three Twin Tube 2-Lane Tunnels, 6 Major Bridges, 11 Minor Bridges and 3 Vehicular Under Passes. The project would be executed on EPC mode and scheduled time of completion of the project is 30 months from the date of commencement.
Powered by Capital Market - Live News