The details of project are as follows:
Sl. No. NH No. Section Length Project Cost (Crore) Contractor's name1 344A 4-Laning of Phagwara - Rupnagar section 81 km Rs. 1444 crore M/s G.R. Infraprojects Ltd.The 81 km long Phagwara - Rupnagar section passes through Banga Town and proposed Nawashahir bypass and terminates at Rupnagar. This will be the shortest route for movement between Amritsar and 'The City Beautiful', Chandigarh, two most important cities of Punjab and also tourist hub for Sikh pilgrimage. The project will help in expediting the improvement of infrastructure in Punjab and in reducing the time and cost of travel.
The project will have 4 structures (Grade separator/flyover), 1 major bridge, 22 minor bridges, one Vehicular Underpass and one Pedestrian Underpass. The project would be executed on Hybrid Annuity mode and scheduled time of completion of project is 30 months from the date of commencement.
Powered by Capital Market - Live News