The Total Capital Cost of the project is Rs 1134.12 Cores. The contract has been awarded to M/s GHV (India) Pvt. Ltd. The project will be carried out on Engineering, Procurement and Construction (EPC) basis and construction period is 24 months. This project has the provision for 9 Minor bridges, 1 ROB, 2 Trumpet Interchanges, 2 Vehicular Underpasses and 11 Light Vehicular Underpasses.
The project stretch falls under Barmer and Jalore districts in the state of Rajasthan. This road is of strategic importance as army vehicles move along this route to the international border area. Development of this stretch will also provide connectivity to remote villages.