NHAI declares Appointed Date as 03 February 2018
Welspun Enterprises announced that the National Highways Authority of India has declared the Appointed Date for the 4-Laning of Gagalheri-Saharanpur-Yamunanagar (UP/Haryana Border) section of NH-73 (Project) as 03 February 2018.The project entails the 4-laning of the 51.5 km stretch, at a bid project cost of Rs.1,184 crore. Under the Concession Agreement, construction of the Project is to be completed within 2 years from the Appointed Date and is to be maintained for 15 years thereafter, post which it will be transferred to NHAI. The EPC contract worth Rs. 1,126 crore will be executed by WEL.
Powered by Capital Market - Live News
Disclaimer: No Business Standard Journalist was involved in creation of this content