Business Standard

Govt sets Feb 15 deadline to put stuck road projects on track

14 projects worth Rs 30,000 cr still stuck despite last week's marathon meeting of bankers and developers to resolve issue

Nitin Gadkari

Nitin Gadkari

Press Trust of India New Delhi
The government has set a deadline of February 15 to resolve the issues stalling highway projects worth Rs 30,000 crore, including fund crunch, Union Minister Nitin Gadkari said.

The remark assumes significance as 14 projects worth Rs 30,000 crore are still stuck despite a marathon meeting of bankers and developers last week to arrive at a solution and with some of these facing termination.

"We have set a deadline of 15 days to solve all issues of stuck 14 highway projects worth about Rs 30,000 crore," Road Transport and Highways Minister Gadkari told PTI.

The projects are stuck due to various issues such as land acquisition, forest and environment clearances, railway over-bridge problems, utility shifting, litigations, delayed decisions and financial problems.
 

When the Narendra Modi government took reins of the government, there were as many as 384 stuck highway projects on account of issues like land acquisition, delay in forest and environment clearances, litigations, equity crunch etc.

"Our efforts led to rolling out of majority of the 384 projects while we had to terminate 41 schemes. Of the remaining 21 languishing projects, issues have been solved for seven while we are confident to resolve issues with remaining 14 within a fortnight," Gadkari said.

Meanwhile, the government is actively considering to terminate seven to eight of the remaining projects, an official said.

This include Panvel-Indapur stretch in Maharashtra, financed by State Bank of India where the developer "does not have equity of Rs 40 crore to access Rs 157 crore of lending", the official said, adding that they suspect fund diversion.

Another project facing termination threat pertains to Rohtak-Jind section in Haryana where "fund diversion" is suspected, the official said.

Yet another project facing termination threat is Rimoli-Roxy-Rajamunda stretch in Odisha where developer "wants cost escalation and extension," he said.

The government is also suspecting "fund diversion" in Walajapet-Poonamalee in Tamil Nadu where arrears of additional concession fee/premium accumulated to Rs 289 crore, he added.

A top official last month had said that banks were "happily over-financing highway projects" and virtually "killed" them and "if developers and bankers fail to mend their ways and initiate correctives to roll out projects, the government will start terminating these.

The projects relate to key national highways in Andhra Pradesh, Bihar, Haryana, Rajasthan, Jharkhand, Karnataka, Madhya Pradesh, Maharashtra, Odisha, Tamil Nadu, Uttarakhand and West Bengal.

The stuck projects belong to players like Larsen & Toubro, HCC, Gammon, Madhucon, Soma and Essel Infra, among others, while the list of lenders includes top names like SBI, Punjab National Bank and Bank of India.

Don't miss the most important news and views of the day. Get them on our Telegram channel

First Published: Jan 31 2016 | 1:13 PM IST

Explore News