HCC bags Rs 217-crore arbitration award from NHAI

Image

Press Trust of India New Delhi
Hindustan Construction Company (HCC) today said it has secured an arbitration award of Rs 217 crore for the extension of time (EOT) cost claim in Lucknow- Muzaffarpur National Highway project.

Of the total award, Rs 135.15 crore is the principal amount and Rs 82.03 crore is the interest component, the company said in a statement.

The three-member arbitration panel, it said, which heard the matter for over 20 months, unanimously ruled that NHAI should pay Rs 217.18 crore to HCC.

The panel also instructed that if the amount is not paid within 90 days, the total amount awarded, including the interest payment, would carry an interest of 15 per cent from the date of award, till the date of payment.
 

HCC had moved the arbitration panel over a delay of 28-month in executing the Rs 255 crore Lucknow-Muzaffarpur Package IV road project. The delay was caused due to non-handing of land in time to execute the work.

The scope of work included 4-laning of 7.25m wide, 29km of bituminous/concrete pavement road on NH-28 between Ayodhya and Gorakhpur.

At present, HCC is lowest bidder in contracts worth Rs 4,733 crore for which the final orders are yet to be received. The order-book position as of December 2014 stands at Rs 14,307 crore.